CR
Environmental, Inc. Pre-
and Post-Dredge Bathymetric
Surveys
of Allen Harbor, Narragansett Bay |
|||
|
In September 1998, CR Environmental, Inc. performed a pre-dredge bathymetric survey of the entrance channel to Allen Harbor at the Naval Construction Battalion Center in Davisville, Rhode Island for Foster Wheeler Environmental Corporation. Two subsequent surveys were conducted in December 1999 and January 2000 to determine the volume of dredge material which had been removed from the channel. CR delivered accurate volume calculations, scaled plans, and digital data. The survey was conducted aboard R/V Cyprinodon using a high-precision digital echosounder, HYPACK survey software and a 12-channel Trimble DGPS. All data were corrected for tidal fluctuations using data collected from a 2-channel vibrating wire transducer pair.
Reference: Dan Sullivan
|
|
||