Nyanza
Wetland Restoration The Nyanza Chemical
Waste Dump Superfund Site is on Megunko Road in the town of Ashland,
Massachusetts.
The Continuous Source Areas
include the Eastern Wetland, Trolley Brook, Outfall Creek, and the Lower
Raceway. Following remediation efforts by Stone & Webster Engineering, CR
Environmental, Inc. provided design and construction oversight for a 5.5 ac
“eastern” wetland mitigation and Trolley Brook construction in 1999. CR restoration specialists reviewed, advised and administered
the Army Corp of Engineers’ work plan, and provided onsite construction
oversight during the grading, planting and stabilization operations.
The unique aspect of this project was the need to manufacture a wetland
soil mixture due to the contamination of the existing organic soils.
Utilizing recycled leaf mulch and sand, the project was able to produce
over 7,880 cubic yards of wetland soil mixture.
A number of wetland cover types were constructed including wooded swamp,
shrub swamp, marsh, and aquatic plantings.
Additional design amenities included vernal pools, constructed ponds and
turtle nesting and basking sites.
|